Prince of Wales Drive CNM – Project Update

Prince of Wales Drive CNM – Project Update June 7, 2017

Work Expected in the Next Two Weeks

Roadway Reconstruction – Strandherd Drive to Fallowfield Road

Roadway reconstruction is scheduled to begin along Prince of Wales, from 480m

north of Strandherd Drive to Fallowfield Road, beginning the evening of Sunday,

June 11th.

This work will require night time construction and nightly closures of northbound

 

Prince of Wales Drive, from Strandherd Drive to Fallowfield Road.

The night work is required to minimize impacts to commuting traffic during the

day, as well as to meet our construction schedule for completion later this year.

The nightly closures of northbound traffic, between 7pm and 5am, will last up to

six (6) weeks, weather-depending. Work at nights are generally scheduled from

Sunday night to Friday morning of each week, however, please note that the

Contractor intends to work the night of Friday, June 16th. Apart from Friday, June

16th, there will be no northbound traffic closures on Friday or Saturday nights.

The Contractor is required to maintain a minimum of one lane of southbound

traffic along Prince of Wales Drive at all times.

The Contractor is required to maintain a minimum of one lane of traffic in each

direction along Prince of Wales Drive between 5am and 7pm every day.

Fairpark Drive Closure

Fairpark Drive at Prince of Wales Drive (west side of intersection) is scheduled to

be closed nightly during the Prince of Wales Drive northbound traffic closures,

between 7pm and 5am, beginning Sunday, June 11th and ending 5am on Friday

June 16th.

Prince of Wales Drive and Waterbridge Intersection

Roadway reconstruction on the east side of the Prince of Wales Drive (POW)

and Waterbridge Intersection began June 5th. The east side of the intersection

will remain closed until Sunday, June 11th.

Roadway reconstruction on the west side of the POW-Waterbridge intersection

will begin the evening of Sunday, June 11th. This work will require a road closure

of Waterbridge Drive at POW for a duration of one week, weather-permitting.

Local residents are recommended to use Crestway Drive for access during this

closure.

Prince of Wales Drive and Crestway/Heathwood Intersection

Roadway reconstruction on the east side of the Prince of Wales Drive (POW)

and Heathwood Gate Intersection is scheduled to begin Sunday, June 18th. This

work will require a road closure of Heathwood Gate at POW for a duration of one

week, weather-permitting. Local residents are recommended to use Waterbridge

Drive for access during this closure.

Roadway reconstruction on the west side of the Prince of Wales Drive (POW)

and Crestway Drive Intersection is scheduled to begin Sunday, June 25th. This

work will require a road closure of Crestway Drive at POW for a duration of one

week, weather-permitting. Local residents are recommended to use Waterbridge

Drive for access during this closure.

Prince of Wales Drive, between Amberwood Crescent and Deakin Street

Utility companies are currently completing the relocation of the overhead

utility line from the west side of Prince of Wales Drive to the east side.

Work is scheduled to continue until early- July 2017

Looking Ahead:

Hunt Club Road at Riverside Drive (East side of intersection)

Construction is scheduled to begin the week of Sunday, June 19th. The work is

currently scheduled to end Sunday, June 25th.

This work will require nighttime construction.

 

Prince of Wales Drive and Merivale Road Intersection

Work along Merivale Road at Prince of Wales Drive is scheduled to begin early-

July 2017.

The construction will require a closure of Merivale Road at Prince of Wales Drive

for two weekends.

Prince of Wales Drive, between Amberwood Crescent and Deakin Street

Construction along Prince of Wales Drive, between Amberwood and Deakin, is

scheduled to begin the week of Sunday, June 18th.

Lane reductions will be implemented for the construction.